Fiberglass pool installation

How we install your fiberglass pool

Plan on about three months from signing to swimming. Most of that is drawings, the city permit and your shell's delivery; the work in your yard usually takes a few weeks.

Concept image: a Latham Olympia 16 fiberglass pool with curving entry steps and a pergola
Latham Olympia 16, AI-generated concept image.

The steps, and how long each takes

StepTimeWhat happens
The visit and the designA free visit, then your written priceJason walks the yard, checks crane access, setbacks and easements, and helps you pick the shell.
DrawingsAbout 2 weeksA drafter who specializes in pools draws the site plan and equipment, including gas sizing for a heater.
City review2 to 4 weeks, depending on the cityMost cities take about two weeks; corrections add about two more. Your HOA approves first if you have one.
The shellDays to about 8 weeksIf the dealer has your model, days. If it's ordered on its own, up to about eight weeks.
The digA few daysEvery utility line located first, including private sprinkler and power lines Blue Stakes won't mark.
The crane setOne dayThe shell is lifted in, set on a level bed of crushed stone, and checked for level.
Fill and backfillDaysWater goes in while stone or sand goes around the outside, rising together so the walls stay straight.
Plumbing, equipment, deckA week or twoLicensed electricians and gas fitters do the electrical and gas work, and the bonding is inspected before the deck covers it.
Cover, inspection, handoverThe last pieceThe automatic cover is usually the last thing installed. Then final inspection and a family walk-through.

Timing is our own experience and plan, not a promise for every yard. Most of the calendar is paperwork and delivery; the work in your yard takes weeks.

How the shell goes in

We follow Latham's installation guide and the shell's independent code evaluation (ICC-ES ESR-2014). In outline:

  1. The hole is dug larger than the shell, so there's room to bed and backfill it properly.
  2. The base is about 4 in. of clean, crushed angular stone or sand, leveled before the shell arrives. Latham's guide also describes a sump at the deep end: perforated pipe to an 8-in. standpipe, a way to check and relieve groundwater later.
  3. The set. The shell is lifted in by crane, using a spreader bar for wide shells, and reset as many times as it takes to sit right and level.
  4. Fill and backfill together. Water goes into the pool while backfill goes around it, kept a few inches below the water as both rise. Doing this right keeps the walls straight, which also matters for the cover track.
  5. Plumbing in 2-in. Schedule 40 PVC on most pools, designed to the drain-entrapment standard.
  6. The bond beam and deck go in after the backfill, on a gravel base and sloped away from the pool.

When the ground is wet or clay

ESR-2014 lets a shell go in without a site soils investigation only if the dig finds none of these: groundwater, uncompacted fill, expansive clay, an unstable slope, or a risk to a nearby structure. If it finds one, the work stops until a design professional has looked at the site. Parts of the Salt Lake Valley have exactly these conditions, so we don't promise "no engineering" before we've seen your ground. Some cities want an engineer regardless: Herriman asks for stamped plans and a soils report after the dig, while Bluffdale accepts the ICC-ES report in place of a stamp.

Getting a 16-ft shell to your street

Anything wider than 8½ ft is an oversize load in Utah and needs a state permit. A 16-ft shell needs a pilot car on the freeway, can only move in daylight, and can't travel during weekday rush hours (6–9 a.m. and 3:30–6 p.m.) in Salt Lake, Davis and Weber counties or in Utah County north of I-15 Exit 261, and never in snow or ice. The hauler handles the permit; we schedule the dig and the crane around it.

What slows a pool down

  • City corrections. Each round adds about two weeks. Clean drawings are the best defense.
  • Shell lead time. Picking a shell the dealer stocks can save weeks.
  • The cover. It's made to your pool's actual measurements, so it's usually the last piece in.
  • Weather. Snow stops deliveries, and cold rules apply to the concrete deck.
  • Change orders. Wanting a built-in spa or a different shell after yours is ordered can mean starting over, and a slide added late means re-planning the deck. Decide before you sign.

Questions

Can you install a fiberglass pool in winter?

Sometimes. The shell itself doesn't mind cold, but oversize loads can't travel in snow or ice, and the concrete deck has cold-weather rules. We suggest signing over the winter to dig in spring.

Why does it take three months if the install is a few weeks?

Because most of the time is paperwork and delivery: about a month for drawings and the city permit, and up to about eight weeks for a shell the dealer doesn't have in stock. We'd rather tell you three months and beat it than promise two weeks and miss.

Will you have to drain the pool later?

Rarely, and never on your own. Latham's paperwork says to keep the shell full and contact Latham before draining, because an empty shell can lift with groundwater pressure. That label goes on your equipment.

Free backyard consultation

Jason’s next open consultation:Wednesday, November 4

Jason books consultations about three weeks out on purpose. Before he walks your yard, he looks up your lot: the plat, the easements, your city’s pool and fence rules, and your HOA. That way the ideas he shows you will actually pass. Request that week or any later one.

Spring 2027 dig dates are booking now.

Families who want to swim by summer usually sign over the winter. Engineering, the permit and HOA approval all come before the first shovel. Herriman’s permit review alone runs 10 to 15 working days.

  • This requests a consultation, not a build date. No deposit, nothing to sign.
  • Jason calls or texts within one business day to set an exact time.
  • No price over the phone. A written price after he has seen your yard.

Rather talk first? Call Jason: 385-202-3342

Which week works?

Jason will call or text to set the time.

So Jason can look up your lot before he comes.

Add a note for Jason

Jason walks your yard with you, answers your questions, and shows you what will fit. No cost and no pressure. We never share your details.

Free backyard consultation

Start with a walk around your yard.

Jason will come out, look at what you’ve got, and show you what’s possible: the pool, the fence, the yard around it. No cost, no pressure, and a written price before anything starts.

Next open consultation: Wednesday, November 4 · or call Jason: 385-202-3342

Book free consultationCall