Building a fiberglass pool in Herriman

Herriman spells out its pool process step by step: a $592.98 permit, 10 to 15 working days of plan review, a structural engineer's stamp, a soils report after the dig, and five inspections before anyone swims. That's good news for you. Every step is written down, so you can check that each one happened.

Herriman’s pool rules

Checked October 2026. Rules change, so we confirm with the city before design.

Permit needed
Pools 24 in. deep or moreSource
Permit fee
$592.98Source
Plan review
10–15 working daysSource
Engineering
Structural engineer's stamp on the plansSource
Soils
Soils report from a licensed geotechnical engineer after excavationSource
Inspections
Five: excavation/footing; combined sub-rough (plumbing, gas, electrical, steel, bonding); rough building/electrical; deck bonding; finalSource
Barrier
Around the pool and the pool equipment; gates swing away from the poolSource
Sample plan
6-ft privacy fence with self-closing, self-locking gatesSource
Door alarms
Shown on the plans where the house is part of the barrierSource
Before use
Final inspection (fences, cover or alarm, bonding) must be approved before the pool is usedSource
Zoning setback
Not published — we confirm with Herriman before design
Utility easements
Waivers from every utility before building in a public utility easementSource
Steps and floor
Step risers 12 in. max; floor slope 33% max; rope and float at the slope break; handholds where deeper than 42 in.Source
Cold-weather concrete
Air-entrained concrete; plaster protected from freezing for at least 24 hoursSource
Bonding ring
#8 copper, 18–20 in. from the inside pool wallSource

What it means for your design

Herriman's checklist sets limits, not comfort. Steps can be 12 inches tall; we'd rather build 10-inch steps that your parents and your four-year-old can both manage. The floor can slope up to 33%; we keep a long, flat shallow end, because a cramped shallow area is one of the regrets owners raise on pool forums.

The barrier has to wrap the equipment too, not just the water. That changes where the pump and filter go. We put the pad inside the fenced yard, and keep it where a pump won't hum under a bedroom window.

Gates swing out, away from the pool, and close and latch by themselves. If a door from the house opens into the pool area, Herriman wants the alarm on the plans. Our approach is the fenced yard: a 6-foot fence on every lot line with self-closing gates, closed against the house, so the house isn't part of the barrier. Herriman's own sample plan shows a 6-ft privacy fence with self-closing, self-locking gates. Every MP pool also gets an automatic safety cover. A barrier that isolates the pool from the house has the strongest evidence behind it for keeping toddlers out.

Five inspections means the schedule follows the inspector. The bonding grid under the deck gets inspected before concrete covers it, so we book the deck pour after that sign-off, not before.

Herriman's cold-weather rule is written for concrete work: air-entrained concrete, and fresh plaster kept from freezing for at least a day. A fiberglass pool has no plaster, but the deck and the bond beam are still concrete, so the cold-weather rule applies to them. If your build runs into the shoulder season, we'll tell you which steps have to wait for warmer weather.

Latham's fiberglass shells carry an ICC-ES evaluation report, ESR-2014, and some cities accept that in place of an engineer's stamp. Herriman isn't one we can lean on it for: it asks for stamped plans and a soils report after the dig regardless, so we plan for both.

Herriman ground and water

Herriman sits inside the area the Utah Geological Survey mapped for western Salt Lake Valley hazards: shallow groundwater, shallow bedrock, and soils that can collapse or swell when they get wet. A map can't tell you what's under one backyard. That's why Herriman asks for the soils report after the dig, when the engineer is looking at the real ground.

After the heavy 2023 snow year, the state survey identified groundwater sites in west Salt Lake County. Snowmelt is one of the named reasons pools lift out of the ground, and an emptied pool shell, fiberglass included, can lift out of the ground when groundwater pushes up on it. Latham's label says to keep the pool full and contact Latham before draining, and its warranty is void if groundwater accumulates under or around the pool. So a Herriman design from us includes a hydrostatic relief valve at the low point and a standpipe you can check before you ever lower the water.

Herriman hands out the county health department's pool-water disposal guide. Backwash and filter-cleaning water go to the sanitary sewer, never a ditch or storm drain. We haven't confirmed which sewer district serves each Herriman street, so we check yours before we place the equipment pad.

Herriman questions

How much is a pool permit in Herriman?

$592.98, per Herriman's pools page when we checked in October 2026. Plan review takes 10 to 15 working days. The engineer's stamp and the soils report are separate costs, and they belong in any written price you're given.

When can we swim in a new pool in Herriman?

After the fifth inspection, the final, passes. Herriman checks the fences, the cover or door alarms and the bonding, and the pool has to be approved before it's used.

Why does Herriman want a soils report after digging?

Because the ground here varies. The state has mapped shallow groundwater and soils that collapse or swell in this part of the valley. A licensed geotechnical engineer looks at your open excavation and confirms the design suits it before the shell is set and the deck steel and concrete go in.

Free backyard consultation

Jason’s next open consultation:Wednesday, November 4

Jason books consultations about three weeks out on purpose. Before he walks your yard, he looks up your lot: the plat, the easements, your city’s pool and fence rules, and your HOA. That way the ideas he shows you will actually pass. Request that week or any later one.

Spring 2027 dig dates are booking now.

Families who want to swim by summer usually sign over the winter. Engineering, the permit and HOA approval all come before the first shovel. Herriman’s permit review alone runs 10 to 15 working days.

  • This requests a consultation, not a build date. No deposit, nothing to sign.
  • Jason calls or texts within one business day to set an exact time.
  • No price over the phone. A written price after he has seen your yard.

Rather talk first? Call Jason: 385-202-3342

Which week works?

Jason will call or text to set the time.

So Jason can look up your lot before he comes.

Add a note for Jason

Jason walks your yard with you, answers your questions, and shows you what will fit. No cost and no pressure. We never share your details.

Free backyard consultation

Start with a walk around your Herriman yard.

Jason will come out, look at what you’ve got, and show you what’s possible: the pool, the fence, the yard around it. No cost, no pressure, and a written price before anything starts.

Next open consultation: Wednesday, November 4 · or call Jason: 385-202-3342

Book free consultationCall